B&M Engineering

Perfection With Every Build

Explore Our Work

Engineering Excellence Since 2021

B&M Engineering delivers end‑to‑end engineering solutions across civil and electrical domains—from residential and industrial electrification to complex railway infrastructure. We build with an unwavering commitment to quality, safety, and on‑time delivery.

Our teams are experienced in OHE foundations, ROCS drilling, high‑voltage cable laying, cable tray systems, station (SSP) infrastructure, and safety systems. We convert complex challenges into reliable, auditable outcomes that exceed client expectations and industry standards.

Guiding Our Path Forward

Our Mission

Deliver top‑tier engineering with zero‑compromise on quality, safety, and compliance—project after project.

Our Vision

Be the trusted partner for reliable, efficient, and innovative civil & electrical solutions across India's growth corridors.

Our Growth Journey

2021–2022: Foundation Era

Established with a 15‑member core team; delivered wiring and lighting projects with consistent quality. Built strong foundation relationships and established our reputation for reliability and precision in electrical installations.

2022–2023: Railway Expansion

Entered railway infrastructure—cable trays, trenching, JB boxes; built capability for complex execution. This strategic pivot opened doors to larger infrastructure projects and established our technical competencies in specialized domains.

2023–Present: Multi‑Domain Delivery

Direct collaborations with Savronik, Tata Constructions, L&T Electricals, and KRCL. Executing OHE foundations, ROCS drilling, and HV cable systems across regions with proven track record of successful project delivery.

The Power Behind Our Success

187
Total Workforce
150
Skilled Workmen
10
Expert Supervisors
5
Licensed Engineers
2
Safety Engineers

Landmark Projects Delivered

OHE Foundations — Chennai

KRCL partnership; executed OHE foundation works with comprehensive QA records and full compliance documentation.

USBRL ROCS Drilling

Precision tunnel drilling from Dharam to Khouri with L&T and Furrer+Frey partnerships, delivering technical excellence in challenging environments.

HT Cable Laying

11 kV & 33 kV systems; copper terminations; 2.5–300 sqmm ranges with full testing and commissioning protocols.

Cable Tray Systems

Comprehensive tray erection and installation across tunnel networks for maintainable routing and optimal cable management.

Tunnel Earth Work (TEW)

Specialized drilling, bolting, clamping, and underground construction works with advanced safety protocols and quality assurance.

Fire‑Fighting Systems

Complete safety infrastructure: advanced detection systems, suppression equipment, and full regulatory compliance.

Specialised Anchoring

Precision M16×170 mm anchor bolt installation with comprehensive pull‑out testing and structural integrity verification.

Fencing & Civil Works

Strategic Savronik partnership for comprehensive corridor security infrastructure and specialized civil construction works.

Station Infrastructure (SSP)

Partnership with L&T: complete station infrastructure including critical 25 kV feeder cable installations and power distribution systems.

Work Orders & Current Projects

Client / Partner WO No. & Date Location & Period Scope (high‑level) Status
Larsen & Toubro (Construction)
KRCL RE work UDMP–SRIN–BRML
LE/LE22MA04/WOD/24/000010
02‑Feb‑2024
Reasi, J&K
01‑Jul‑2023 → 01‑Sep‑2024
Labour subcontractor services for KRCL USBRL project incl. OHE/OPGW assistance & execution. Completed
Larsen & Toubro (Construction)
KRCL RE work UDMP–SRIN–BRML
LE/LE22MA04/WOD/24/000084
24‑Jul‑2024
Reasi, J&K
01‑Mar‑2024 → 31‑Oct‑2024
OPGW/OHE stringing & electrical earthing (~8,300 m) with terminations and fittings. Completed
Larsen & Toubro (Construction)
KRCL RE work UDMP–SRIN–BRML
LE/LE22MA04/WOD/24/000093
27‑Aug‑2024
Reasi, J&K
01‑Jul‑2024 → 31‑Oct‑2024
Feeder wire (Cu) stringing (~1,500 rm) with termination at both ends; specialised tools/P&M. Completed
Shree Electrical Engineer (I) Pvt. Ltd.
USBRL Project
SEEIPL/JK/KRCL/023/Sangaldan
22‑Sep‑2023
Sangaldan, J&K SITC of 11 kV 3C×185 sqmm cable with trays/supports, GI flat earthing & testing; minor civil (M10). Completed
Shree Electrical Engineer (I) Pvt. Ltd.
USBRL Project
WO (Ref. on file) Sangaldan, J&K Cable tray installation & power/control cable laying with testing and documentation. Completed
Furrer & Frey India
Overhead Contact Lines
PO/WO (ref. on file) J&K & associated rail corridors Supply of anchor bolts, templates & tools; supervision & OCS execution support. Partner Delivery
Piscesia Savronik JV (Savronik)
Railway Corridor Security
PSJV/KONT40/20/PO/217‑A1
15‑Jul‑2024
Konkan T40 — Multiple locations Fencing & civil works: guard bars, chain link, excavation, PCC/RCC, shuttering, MS pipe, sand, cement. Executed
Konkan Railway Corporation Ltd. (KRCL)
Corporate Office — Electrical
KR‑CO‑EL‑MAS‑RU‑T‑02‑25 (LOA)
30‑Jan‑2025
Chennai–Renigunta (SR) Cement concrete for OHE foundations & plinths — 37.5 CUM (hard & rocky), 25 CUM (rocky), 2,500 CUM (other). Ongoing
Linxon India Pvt. Ltd.
CMRL Phase‑II OHE‑10
PO 22429 (Rev 0)
22‑Jul‑2025
Perumbakkam RSS, Chennai
Target: ~2 months
DRPC Building & Equipment civil works per approved drawings/BOQ/FQP; HSE & quality per Linxon/CMRL. Ongoing

Key operational details displayed; commercial values intentionally omitted for confidentiality.

Current Deployment & Workforce Details

RoleCountProject / SiteCoverageLead
Civil Foundation Workers 60 Chennai — 2×25 kV OHE Foundations Active Operations Site In‑Charge (Civil)
Civil Engineers 2 Chennai Corridor Quality & DPR Management Project Engineer (Civil)
OHE Supervisors 2 Chennai Corridor OHE Stringing & Safety Sr. OHE Supervisor

Operational Framework: Specialized crews organized for excavation, PCC/RCC works, reinforcement installation, shuttering operations, and comprehensive QA/DPR maintenance to ensure consistent safety standards and daily output targets.

Work Done (Key Milestones)

Completed Projects

COMPLETED

Feeder Wire Stringing

~1,500 rm with precision termination at both ends (Jul–Oct 2024). Full quality documentation and testing protocols completed.

COMPLETED

OPGW/OHE & Earthing

~8,300 m executed with comprehensive accessories installation and complete QA record maintenance.

COMPLETED

11 kV Distribution Network

55 km successfully executed with full commissioning and performance verification.

COMPLETED

33 kV Distribution Network

40 km executed with advanced testing protocols and regulatory compliance documentation.

COMPLETED

Power & Control Cable Systems

2.5–120 sqmm range professionally installed in partnership with M/S BAB as specialized subcontractor.

COMPLETED

SSP Buildings — Electrical Infrastructure

Successfully delivered in strategic partnership with Larsen & Toubro (L&T) with full system integration.

COMPLETED

Earthing Systems Installation

5 km of earthing flats executed in collaboration with Shree Electrical Engineer (I) Pvt. Ltd.

COMPLETED

Cable Management Systems

Comprehensive cable trays and cable laying executed under dedicated work order with Shree Electrical Engineer (I) Pvt. Ltd.

Active Operations

ONGOING

Chennai OHE Foundation Works

Advanced foundation & plinth concreting operations as per LOA KR‑CO‑EL‑MAS‑RU‑T‑02‑25 with specialized concrete grade requirements.

ONGOING

CMRL Phase‑II OHE‑10 (Linxon Partnership)

DRPC Building & Equipment civil construction at Perumbakkam RSS, Chennai — executing per PO 22429 (Rev 0, dated 22‑Jul‑2025). Target completion: ~2 months.